Steel workers are installing a beam as part of the cantileaver.

Children’s Memorial Hospital is committed to keeping the community informed about the progress of construction on Ann & Robert H. Lurie Children’s Hospital of Chicago through e-mail alerts, an electronic newsletter, community meetings and regular updates to our website.

July construction update

Children’s Memorial Hospital continues construction on Ann & Robert H. Lurie Children’s Hospital of Chicago at 225 E. Chicago Ave. (next to Northwestern Memorial’s Prentice Women’s Hospital). 

In July, we will continue finishing up the exterior work.  Almost all of the pre-cast (skin of the building) and windows have been installed.  In addition, there is significant interior work taking place on each floor. On the upper levels, drywall is being installed, and plumbing and electrical work continues. On the lower levels, workers are painting walls, protecting and sealing floors, and preparing for installation of cabinets. Also, construction continues on the 5th floor bridge connecting Lurie Children's to Prentice Women's Hospital (all work to be done on site); as well as the 2nd floor pedestrian bridge connecting Lurie Children’s, Prentice and the parking garage for families and visitors.

Due to the nature of the work related to the installation of the pedestrian bridge across Superior St, lane or street closures will be required in the area in front of the parking garage during portions of the project. Below is the anticipated schedule.   

 

ANTICIPATED SCHEDULE:

Superior St. Bridge Installation:
June 1, 2010 - March 1, 2011 (target date subject to weather, etc.)

Temporary Partial Closures of Superior St. Traffic Lane in Front of Parking Garage:
May 31 - August 16, 2010

Temporary Weekend Full Closures of Superior St. Traffic Lanes in Front of Parking Garage from 7 a.m.-7 p.m. (subject to weather, etc.):
July 24-25, 2010
July 31-August 1, 2010
August 14-15, 2010
Early 2011 (TBD)

During July, work will continue to occur Monday through Friday from 8 a.m. to late afternoon or early evening, and Saturdays from 8 a.m. to late afternoon.  Work on Sundays is also likely to continue timely completion of construction.  You may notice increased truck activity related to deliveries.  All work will be performed consistent with the City noise code requirements.

 Archived construction updates »

May 5, 2010 Community Presentation

Children's Memorial held the 3rd Annual Construction Update meeting about 2010 construction plans for Ann & Robert H. Lurie Children’s Hospital of Chicago. Hospital leaders and our construction management team presented plans and answered questions about the new building.

Contact

For more information, or to be added to the monthly construction update list, contact Nahlah Daddino, Director of Community Relations, 773.975.8733.

For emergencies related to the building or construction site, contact Children’s Memorial's Construction Hotline at 773.880.4100.